Construction Preliminaries: What Builders Should Include in a Project Estimate

Construction preliminaries and site establishment on an Australian building project

Construction estimates are often built around measurable work such as concrete, framing, roofing, finishes, services and labour. However, a project also requires a range of costs before and during construction that do not form part of the permanent building itself.


These costs are generally known as construction preliminaries.


Preliminaries can cover everything from establishing the site and providing temporary power and water to site supervision, security, safety measures, temporary facilities and project administration. If these costs are missed or underestimated, a tender can look competitive on paper while leaving the builder with a much smaller margin than expected.


For Australian builders and contractors, allowing for preliminaries accurately is therefore an important part of preparing a realistic construction estimate.

What Are Construction Preliminaries?

Construction preliminaries are the temporary and project-specific costs required to establish, operate and manage a construction site. They can include site establishment, temporary power and water, site facilities, supervision, safety and compliance, security, site access and logistics, temporary works, and applicable permits or project requirements.


The exact construction preliminaries costs vary depending on the project type, location, site conditions, construction duration and contract requirements. Builders should identify these costs during the estimating process rather than adding a general allowance at the end.

Why Preliminaries Matter in Project Estimating

A construction estimate is only useful if it reflects the actual resources required to deliver the project.


Leaving out preliminary costs can create several problems:


  • The tender price may be artificially low.
  • Project overheads may not be recovered.
  • Gross profit can be reduced.
  • Cash-flow requirements can be underestimated.
  • Site management costs can become difficult to absorb.
  • Variations and extensions of time may create additional exposure.
  • The builder may need to recover unexpected costs elsewhere.

Preliminaries are particularly important when comparing projects with different construction durations.


For example, a project that requires six months of site supervision will generally have different preliminary requirements from a similar project that takes 18 months. Some preliminary costs are fixed or mobilisation-related, while others continue for every week or month that the site remains operational.


This means builders should avoid simply applying a blanket percentage without first considering the actual project requirements.

Major Categories of Preliminary Costs

1. Site Establishment

Site establishment is usually one of the first groups of site preliminaries to consider.

 

 

Depending on the project, this can include:

 

 

  • Site mobilisation
  • Temporary fencing and hoarding
  • Site signage
  • Site access preparation
  • Site office setup
  • Temporary storage areas
  • Delivery areas
  • Initial site cleaning
  • Establishment of worker facilities
  • Mobilisation of plant and equipment

The site location can have a major effect on these costs.

 

A constrained urban site may require more planning for deliveries, storage and access than a larger suburban or regional site.

2. Temporary Services

Construction sites often need temporary services before permanent building services become available.

 

 

Potential allowances include:

 

 

  • Temporary electricity
  • Temporary lighting
  • Temporary water
  • Temporary drainage arrangements
  • Temporary communications
  • Internet or data services
  • Temporary power distribution
  • Generator hire where required

Builders should consider both installation and ongoing operating costs.

 

For longer projects, temporary services can become a significant component of construction preliminaries costs, particularly where the site has limited existing infrastructure.

3. Site Facilities

Workers and site personnel require appropriate facilities throughout construction.

 

Depending on the project, this may include:

 

  • Site offices
  • Portable toilets
  • Lunch or crib rooms
  • Change rooms
  • Storage facilities
  • First-aid facilities
  • Temporary amenities
  • Furniture and office equipment

Some facilities may be hired for the duration of the project rather than purchased.

When preparing an estimate, the expected construction period should therefore be considered alongside the required facilities.

4. Supervision and Project Management

Labour associated with the permanent construction works is generally measured within the relevant trade packages. Site management is different.


Preliminary allowances may need to account for personnel such as:

 

  • Site supervisors
  • Site managers
  • Project managers
  • Foremen
  • Site administrators
  • Safety personnel where required
  • Other project-specific management resources


The appropriate allowance depends on the project’s scale and complexity.


A small residential project may require limited supervision, while a large commercial project can require dedicated site management throughout the construction period.


This is one reason construction project preliminaries should be assessed against the programme rather than estimated solely from the building’s floor area.

5. Safety and Compliance

Safety requirements can generate a range of preliminary costs.

 

Depending on the project, allowances may include:

 

  • Site safety signage
  • Safety barriers
  • Temporary edge protection
  • Site inductions
  • Personal protective equipment for relevant personnel
  • Safety documentation and administration
  • Emergency equipment
  • Site inspections
  • Traffic and pedestrian separation measures

The specific requirements will vary according to the project, site conditions and applicable Australian requirements.

 

Builders should review the project documentation and site conditions carefully rather than relying on a generic allowance.

6. Security

Site security can become particularly important for projects involving valuable materials, equipment or restricted urban sites.

 

Potential costs include:

  • Temporary fencing
  • Security gates
  • Locks and access controls
  • Security lighting
  • Alarm systems
  • Security monitoring
  • Temporary surveillance systems
  • After-hours security arrangements

Security requirements may also change as construction progresses.

 

For example, a project storing high-value materials or equipment on site may require stronger controls than a smaller project with limited stored materials.

7. Site Access and Logistics

Access and logistics are often underestimated because they do not always appear as obvious construction quantities.

 

Depending on the project, preliminary allowances may include:

 

  • Traffic management
  • Temporary access roads
  • Delivery coordination
  • Loading and unloading arrangements
  • Crane or hoist access
  • Material handling
  • Site logistics management
  • Temporary pedestrian controls
  • Road or footpath protection
  • Delivery restrictions

Urban construction sites can be especially challenging because deliveries may need to be coordinated around traffic, neighbouring properties and restricted working areas.

 

The estimator should therefore review the site constraints before finalising the preliminary allowance.

8. Temporary Works

Temporary works support construction but are not necessarily part of the finished project.

 

Examples can include:

  • Temporary propping
  • Temporary access platforms
  • Temporary weather protection
  • Temporary barriers
  • Temporary retaining arrangements
  • Temporary protection systems
  • Temporary structural support
  • Temporary work platforms

Not every project requires the same temporary works.

 

Where engineering, staging or site conditions indicate that temporary works will be required, they should be identified during estimating rather than assumed to be absorbed within trade costs.

9. Insurance, Permits and Other Project Requirements

Some projects may also involve project-specific costs associated with:

 

  • Permits and approvals
  • Inspections and fees
  • Required certificates
  • Project insurance arrangements
  • Bonding or security requirements
  • Environmental controls
  • Testing and compliance requirements

These items should be checked against the contract, tender documentation and project requirements.

 

 

Not every permit, fee or insurance cost belongs under preliminaries on every project, so the estimator should establish who is responsible for each cost before including it in the tender.

What Builders Often Forget to Include

Some construction preliminary costs are easy to overlook because they are relatively small individually.


Common omissions include:


Site setup and removal
Builders may allow for establishing the site but forget the cost of demobilisation and removing temporary facilities at the end of the project.


Temporary utilities
Temporary electricity and water can continue for months. An allowance based only on initial connection costs may therefore be insufficient.


Site cleaning and waste
Ongoing cleaning, waste collection and disposal can continue throughout the construction period.


Security
Security requirements can increase as valuable materials, plant and equipment are delivered.


Site management
Supervision costs should reflect the actual programme rather than being treated as a minor miscellaneous expense.


Extended project duration
If the project runs longer than expected, many preliminary costs continue accumulating. This makes the construction programme an important part of preliminary cost planning.

How to Estimate Preliminaries Accurately

A practical approach is to build preliminaries from the actual project requirements rather than applying one percentage automatically.

Step 1: Review the project documentation

Start with:

 

  • Architectural drawings
  • Engineering documentation
  • Specifications
  • Tender conditions
  • Contract requirements
  • Site information
  • Construction programme
  • Existing services information

Look for requirements that could generate temporary or project-wide costs.

Step 2: Understand the site

Consider:

 

  • Site location
  • Access restrictions
  • Existing buildings
  • Neighbouring properties
  • Available utilities
  • Storage limitations
  • Traffic conditions
  • Site security
  • Environmental constraints

A difficult site can require significantly more preliminary planning than a straightforward site.

Step 3: Establish the construction duration

Separate costs into those that are:


Fixed or mobilisation-related:
Such as initial site setup, mobilisation and establishment.


Time-related:
Such as site supervision, temporary facilities, security, temporary services and site management.


This distinction makes the estimate more responsive to programme changes.

Step 4: Assign responsibility

Review each preliminary item and establish whether it is:

 

  • Builder’s cost
  • Client’s cost
  • Consultant’s cost
  • Included in a subcontractor’s scope
  • Excluded under the contract

This helps prevent both omissions and double counting.

Step 5: Obtain realistic supplier and subcontractor pricing

Where possible, obtain current quotations for items such as:

 

  • Temporary fencing
  • Portable amenities
  • Security
  • Plant hire
  • Temporary power
  • Traffic management
  • Waste services

Current supplier pricing is generally more reliable than relying on outdated allowances.

Step 6: Review the estimate before tender submission

Perform a dedicated preliminary-cost review before finalising the tender.


Ask:


Can this project actually be established, operated, supervised and secured for the amount currently allowed?


That question can reveal gaps that are not obvious when reviewing individual trade packages.

Example Preliminary Cost Breakdown

The following example demonstrates how a builder might organise preliminary costs for a hypothetical project. It is an estimating structure, not a standard industry percentage or benchmark.

 

Preliminary category

Example allowance

Site establishment and mobilisation

$18,000

Temporary fencing and signage

$8,000

Temporary power and water

$7,500

Site office and amenities

$15,000

Site supervision and management

$55,000

Safety and compliance

$6,500

Security

$5,000

Traffic and site logistics

$12,000

Temporary works

$10,000

Cleaning and waste management

$8,000

Demobilisation

$5,000

Example total

$150,000

The actual allowance could be significantly higher or lower depending on project size, duration, location, complexity and contract requirements.


The important point is to build the allowance from identifiable costs rather than treating preliminaries as an unexplained percentage.

Preliminaries vs Direct Construction Costs

One of the easiest ways to understand preliminaries is to compare them with direct construction costs.

 

Direct construction costs are generally associated with the physical work and permanent components of the project.

 

Examples include:

 

  • Concrete
  • Reinforcement
  • Brickwork
  • Carpentry
  • Roofing
  • Plasterboard
  • Painting
  • Plumbing
  • Electrical installation
  • Mechanical services

Preliminaries support the delivery of that work.

 

Examples include:

 

  • Site establishment
  • Temporary facilities
  • Site supervision
  • Temporary services
  • Security
  • Site logistics
  • Safety administration
  • Temporary works

The distinction matters because preliminary costs can otherwise become hidden inside trade allowances, making it harder to understand the true cost structure of the project.

 

For a broader overview of what should appear in a construction estimate, builders can also refer to Can Estimating’s guide on what should be included in a construction estimate.

Practical Construction Preliminaries Checklist

Before submitting a tender, review whether the estimate addresses:

  • Site mobilisation
  • Site establishment
  • Temporary fencing and hoarding
  • Site signage
  • Temporary power
  • Temporary water
  • Temporary lighting
  • Site office
  • Worker amenities
  • Site supervision
  • Project management
  • Safety requirements
  • Security
  • Traffic management
  • Site access and logistics
  • Temporary works
  • Waste management
  • Site cleaning
  • Applicable permits and fees
  • Relevant insurance requirements
  • Demobilisation
  • Construction programme duration
  • Potential time-related preliminary costs

The checklist should be adjusted for the project’s scope and contract conditions.

Key Takeaways for Builders

Construction preliminaries are an important part of producing a realistic project estimate.

 

The main lessons are:

 

 

  • Do not treat preliminaries as an afterthought. Identify them during the initial estimating process.

  • Review the actual site conditions. Access, location, services and constraints can significantly affect preliminary costs.

  • Separate fixed and time-related costs. This makes the estimate more accurate when project duration changes.

  • Check contract responsibilities. Confirm which party is responsible for permits, facilities, temporary works and other project requirements.

  • Avoid unexplained percentage allowances. Build preliminaries from identifiable project costs wherever practical.

  • Review the programme. Longer construction periods can increase supervision, security, temporary services and facility costs.

  • Complete a dedicated preliminary-cost review before tender submission.

For builders managing multiple tenders or complex projects, professional estimating support can help ensure project-wide costs are identified alongside the individual trade quantities. Can Estimating provides construction estimating services for Australian construction projects and can assist with structured cost estimating and tender preparation.

Frequently Asked Questions About Construction Preliminaries

What are preliminaries in construction?

Preliminaries are the costs required to establish, manage, operate and support a construction project that are not normally part of the permanent construction works. They can include site establishment, temporary services, site facilities, supervision, safety, security and logistics.

What is included in construction preliminaries?

Typical construction preliminaries can include site establishment, temporary power and water, site offices, amenities, supervision, project management, safety requirements, security, traffic management, temporary works, waste management and demobilisation. The exact scope depends on the project and contract.

How are construction preliminaries calculated?

Preliminaries can be calculated by identifying individual project requirements and assigning costs to them. Some are fixed costs, while others depend on the construction duration. A percentage allowance may be used in some estimating approaches, but it should be supported by the project’s actual requirements.

Are preliminaries direct construction costs?

Generally, preliminaries are not the same as direct construction costs. Direct costs relate primarily to the permanent works, while preliminaries cover the temporary and project-wide resources required to deliver those works.

Why are preliminaries important in construction estimating?

Preliminaries help builders account for the costs of operating and managing a construction site. Omitting them can result in an unrealistically low tender price and reduce the builder’s expected margin.

Do residential and commercial projects have the same preliminary costs?

No. Preliminary requirements vary according to project size, construction duration, location, site constraints, complexity and contract conditions. A large commercial development may require considerably more site management and logistics than a smaller residential project.

Can preliminaries change during construction?

Yes. Costs can increase when a project is delayed or extended because some preliminary expenses, such as site supervision, temporary facilities, security and temporary services, are time-related.